Published On: 07 May 19
The Botanic structural slab level is now at Level 6 and the lift core structure ...
Published On: 11 Mar 19
Icon continue to make progress on site at 25 – 29 Coventry Street. The formwork ...
Published On: 14 Jan 19
We are really pleased with the progress at Botanic in the 12 months since demolition ...
Published On: 12 Sep 18
Icon has made great progress on site. The excavation and retention system was completed in ...
Published On: 30 Jul 18
The crane has been installed at Botanic (the install was completed over 2 days). Excavation ...
Published On: 26 Jun 18
Demolition was completed at the end of March and Icon commenced on site in April. ...
Published On: 18 Mar 18
In 2018, Evolve Development celebrates its 15th Year of developing property. Our passion as a ...
Published On: 24 Feb 18
Demolition is almost complete and we anticipate Icon Co (Project Builder) to be situated onsite ...
Published On: 08 Dec 17
The Botanic Melbourne display suite will be closing this weekend 9th December – 10th Dec ...
Published On: 28 Nov 17
Evolve Development are thrilled to have Icon Co on board as the Project Builder. Icon ...